KBA-01502: Project Dates

Question:

How do I use the Project Date Types?

Answer:

There are two date types distributed for use on the Project Setup document.

  • Project Current – Start and End dates.  These dates are copied to Commitments from the Project Setup by default.
    • Start Date — the contractual start date
    • Finish Date – this is generally the contractual substantial completion date of the project.  Change orders can automatically increment this date — see ProjectConfig TrackCODays
  • Project Closeout – A single (finish) date.  This can represent a date usually beyond the substantial completion date of the project.

KBA-01502; Last updated: April 14, 2022 at 20:58 pm
Keywords:  substantial completion date