Production Analysis Report

This report lists Cost Codes and information related to Production Units, using data from the Financial Snapshot associated with the most recently posted Production Entry.

Production Analysis Report

Note: although the image above does not show the Output drop-down, you can select an output method (PDF/Excel/CSV) for this report.

Filters

  • Project – the Project ID.  You can look up or type a specific project ID, or use the % mask for multiple projects.
  • Cost Code – the Cost Code associated with the Production Unit.  You can enter a specific Cost Code or use the % mask for multiple Cost Codes.
  • As Of – this hidden filter is passed from a Production Entry document.  If the report is run from the report browser, the most recently “approved” Production Entry is used.   Any EAC/FAC changes after the most recent Production Entry document are ignored.

Column

  • WBS Code – the Cost Code number and description.
  • Budget:Dollars – the EAC amount
  • Budget: MH –  the sum of the EAC Man Hours for the Cost Code
  • Budget: Units – the total EAC Units for the Cost Code
  • Budget: UOM – the Cost Code line’s Unit of Measure
  • Budget: Unit Cost – the Budget amount divided by the Budget Units
  • Budget: MH/Unit – the Budget Man Hours divided by the Budget Units
  • Actuals to Date: Cost – Actual costs accumulated on this Cost Code for all Account Categories
  • Actuals to Date: MH – Actual Man Hours accumulated on this Cost Code for all labor-type Account Categories
  • Actuals to Date: Units – the Units Produced (from Production Unit documents or posted Forecasts)
  • Actuals to Date: Unit Cost – Actual to Date Costs divided by Actual to Date Units
  • Actuals to Date: Cost Factor – Actuals to Date Unit Cost divided by Budget Unit Cost
  • Actuals to Date: MH Units – Actual to Date Man Hours divided by Actual to Date Units
  • Actuals to Date: Prod Factor – Actual to Date MH Units divided by Budget MH/Unit
  • ETC: Dollars/Unit – Estimate To Complete (EAC) amount divided by Units.
  • ETC: MH/Unit – EAC Man Hours divided by Units
  • FAC: Dollars/Unit – FAC (Forecast to Completion) amount divided by Units.  Says same if the FAC equals the EAC
  • FAC: MH/Unit – the FAC Man Hours divided by Units.