KBA-01843: Tracking Retainer Amounts in the SOV WorkbookKBA-01843: Tracking Retainer Amounts in the SOV Workbook

Problem: If your company receives a retainer as part of a contract, you may have wondered how to track that amount in Spitfire. The retainer is money received that is

Inactive/Closed/Completed ProjectsInactive/Closed/Completed Projects

Question: I have some projects in Spitfire that are no longer active. How can I mark them as inactive? Also, will I be able to access those inactive projects in

Calculating Start and Finish Dates on Dates TabCalculating Start and Finish Dates on Dates Tab

Question: When we start Commitments/Subcontracts, we know how many days we expect the work to take. Can Spitfire calculate the Finish date or required Start date with this information? Answer:

Automatic Markup of Change Order CI Budget EntriesAutomatic Markup of Change Order CI Budget Entries

Did You Know? You can set up one or more markup percentages for the Budget Entries on CO Change Items, if you do not want to enter markups manually. The