Question: What does the message “Register is empty: create item(s) now” mean? Answer: You tried to open either the Submittal Item Register or the Change Item Register, but they do
Question: At my company, the CCO for the Commitment always comes in first, before the Change Order. Here’s our workflow: We create the CCO according to the paperwork that is
Question: How does Spitfire determine the Contract line for Change Items? Can I establish a default Contract line for all my Change Items? Answer: The Contract line on a Change Item
Problem: Your Project Setup document is Committed, and Change Orders have been created. Therefore the Create SOV option is not available on the Project Setup‘s drop-down Options menu. Solution: If using
Question: When I create a Change Order document, the lookup for my Account Categories is blank. Why? Answer: sfPMS includes only those Account Categories that have been designated for Change Orders
Question: Can I disable automatic budget revisions created for project Change Orders? Answer: Of course! Open the Rules Maintenance Tool on the System Admin Dashboard. Expand the Budget Config rule
Question: I know I can create a Commitment Change Order (CCO) from a Proposed Change Order or a Change Order, but can I create a CCO independently without creating a
Question: How does Spitfire determine the default revenue code for Change Items? Answer: The Revenue Code on a Change Item determines where in the WBS/Budget any additional revenue associated with
Question: How do I use sequence in the allocation rules for Change Items? Answer: The sequence field in allocation rules is used to control both how the allocation rules are