This report lists how Commitment line Items compare to the budget. This report is available from a Commitment or CCO’s Option menu (Commitment-vs-Budget) as well as the Report Browser. Note: a
Question: How does a Commitment or a Commitment Change Order (CCO) update the budget? Answer: When appropriate, the Commitment and CCO will create Budget Revision (and/or) Forecast documents to update
Purpose & Scope: Freight on a Commitment is often unknown at the time the Commitment is established with the subcontractor. Providing freight items with a special Account Category and item
Purpose & Scope: You may sometimes find that the value of a subcontract is accurate, but the Open Commitment is calculating the wrong amount. Why? Possible Issues: The subcontract contains
Question: When I add an Item on a Commitment/Subcontract, the Sub Account field automatically populates. But where does this Sub Account come from? Answer: In Microsoft Dynamics SL, the Sub
Problem: Can the Item amounts be displayed in the Item Grid View on the Commitment document? Solution: To display Item Amounts in the Item Grid View, use the Customization tool, found
Question: How do I create a Commitment or CCO from an RFQ? When does the system create a CCO from an RFQ? Answer: When it is time to take an
Question: Some of my subcontractors start at 12% retention and we reduce this to 10% then 5% as the project progresses. How do I allow this in Spitfire? Answer: Users
Question: When I enter an Item on a Commitment, sometimes the GL Account automatically populates and sometimes it doesn‘t. Where does the GL Account come from? Answer: On a Commitment